Utah Commissioner Seeks More Scrutiny of State USF Costs
The Utah Public Service Commission set an April 5 technical conference on possibly tightening requirements for seeking state USF support. The Utah PSC said it opened docket 24-999-10 in response to Commissioner John Harvey’s request that the commission get more evidence showing that costs claimed by a telecom company to receive support are reasonable. Harvey suggested that this includes a showing that the utility has applied for federal funds that could offset broadband costs and that any broadband speed the company provides above the federal minimum “has been done without incurring additional costs … or that such extra costs are either insignificant (compared to the total costs of the project), or that the extra costs can be justified by other public policy considerations," the PSC said. Also, Harvey wants to see utilities show their network design “is the least cost design” and that they chose the lesser cost "option of self-construction versus contracted construction,” it said.